TR long-range crew forecast through 2030

—

Days at or above 80% of crews busy —
—of working days in the quarter
Fleet utilization —
—of 80% goal——
Long-range unit jobs placed—
Openings for new work, through May 2028 — openings

What the plan saves

The same jobs, durations and calendar rules, scheduled two ways. Baseline: each unit goes to the crew that can start soonest, the closest one if several tie, which is how a dispatcher picks without the tool. Plan: this forecast, which picks the crew that adds the fewest miles. Preferred crews and overrides apply to both. Durations are assumed by scope, so every figure is an estimate.

Rig miles saved—
Haul days saved—Crew-days back on work instead of driving
Estimated value—Diesel plus crew time on haul days
Diesel saved—
Carbon emissions saved— metric t— kg · — lb, at 10.21 kg CO₂ per gallon of diesel (EPA)Like taking — cars off the road for a year, or growing — trees for 10 years (EPA)

—

Rig miles by quarter: soonest-crew baseline vs. plan

BaselinePlanFaded = beyond the 18-month booking horizon

—

Crew supply vs. booked work, by quarter

Available = 19 crews × days outside the Dec 18 – Jan 4 shutdown. Booked = Eric’s near-term schedule plus long-range placements. Informational only: no quarter is flagged. For context, suggested starting points for leadership to set the tipping points are a shortage above 90% utilization (no room for slips; time to hire or subcontract) and a surplus below 70% inside the booking horizon (a cue for sales). Quarters past the 18-month booking horizon show bookings that haven’t arrived yet, not idle crews.

QuarterAvailable crew-daysBooked crew-daysUtilizationCrews busy (of 19)Crews openView

Where the work is, by year

Share of crew-days by region, by start year. Use it to check the laydown yards still sit where the work is going. The current quarter is left out.

Fleet utilization by quarter

Booked crew-days ÷ available crew-days across 19 crews (Dec 18 – Jan 4 blackout excluded). Grey = Eric's near-term schedule, color = long-range placements, dashed line = 80% goal. Faded bars are past the 18-month booking horizon: bookings haven’t arrived yet, so low numbers there are not idle capacity.

Utilization by crew, next 4 quarters

Same measure per crew. Darker = busier. Later quarters are left out because crew assignments that far ahead come from the placement rules, not real assignments.

Idle gaps, next 18 months

Stretches of 10+ working days (Mon–Fri, outside the shutdown) between a crew’s jobs, inside the booking horizon. Each gap shows the jobs and sites on either side, so new work can be sold near where the crew already is. Drive days = days needed to move between the two sites.

CrewGap startGap endWorking daysDrive daysJob beforeSite beforeJob afterSite afterID

Crew schedule

Near-term (fixed)Long-range D&T / serviceM&D pairedSite TBD

Job list

Every unit placement from next quarter on. All long-range durations are ASSUMED by scope (D&T 14d, I&C 10, Commissioning 5, Warranty 4, M&D 2) until the cost model replaces them.

CrewStartFinishDaysJobObjectCustomerPMSiteWorkSourceStart basisFlagsID

· Long-range placements are estimates: durations are assumed by scope and drive distances are straight-line × 1.28. Internal use only.