The same jobs, durations and calendar rules, scheduled two ways. Baseline: each unit goes to the crew that can start soonest, the closest one if several tie, which is how a dispatcher picks without the tool. Plan: this forecast, which picks the crew that adds the fewest miles. Preferred crews and overrides apply to both. Durations are assumed by scope, so every figure is an estimate.
—
—
Available = 19 crews × days outside the Dec 18 – Jan 4 shutdown. Booked = Eric’s near-term schedule plus long-range placements. Informational only: no quarter is flagged. For context, suggested starting points for leadership to set the tipping points are a shortage above 90% utilization (no room for slips; time to hire or subcontract) and a surplus below 70% inside the booking horizon (a cue for sales). Quarters past the 18-month booking horizon show bookings that haven’t arrived yet, not idle crews.
| Quarter | Available crew-days | Booked crew-days | Utilization | Crews busy (of 19) | Crews open | View |
|---|
Share of crew-days by region, by start year. Use it to check the laydown yards still sit where the work is going. The current quarter is left out.
Booked crew-days ÷ available crew-days across 19 crews (Dec 18 – Jan 4 blackout excluded). Grey = Eric's near-term schedule, color = long-range placements, dashed line = 80% goal. Faded bars are past the 18-month booking horizon: bookings haven’t arrived yet, so low numbers there are not idle capacity.
Same measure per crew. Darker = busier. Later quarters are left out because crew assignments that far ahead come from the placement rules, not real assignments.
Stretches of 10+ working days (Mon–Fri, outside the shutdown) between a crew’s jobs, inside the booking horizon. Each gap shows the jobs and sites on either side, so new work can be sold near where the crew already is. Drive days = days needed to move between the two sites.
| Crew | Gap start | Gap end | Working days | Drive days | Job before | Site before | Job after | Site after | ID |
|---|
Every unit placement from next quarter on. All long-range durations are ASSUMED by scope (D&T 14d, I&C 10, Commissioning 5, Warranty 4, M&D 2) until the cost model replaces them.
| Crew | Start | Finish | Days | Job | Object | Customer | PM | Site | Work | Source | Start basis | Flags | ID |
|---|
· Long-range placements are estimates: durations are assumed by scope and drive distances are straight-line × 1.28. Internal use only.